Highway Sheet 01
-
1) Question.
If the gradient of a sloping road is 1 in 30 then the camber to be provided is
Answer. -
2) Question.
If the coefficient of friction and r eaction time of the driver are respectively 0.4 and 2.5 secs and the design speed in 50 km per hour, the minimum sight distance to be provided, is,
Answer. -
3) Question.
The stopping sight distance in which a vehicle can be brought to a stop, depends upon
Answer. -
4) Question.
On two lane highways where the width is ofthe order of 7 metres or more, the following type of road camber is sutable
Answer. -
5) Question.
Assuming the reaction time t for a speed of 80 km per hour, as 2.50 seconds, then, the reaction distance is
Answer. -
6) Question.
The maximum number of passenger cars than can pass a given point on a road way during one hourunderthe most ideal roadway and traffic condition, is called
Answer. -
7) Question.
Enoscope is used to determine
Answer. -
8) Question.
The length of a the side of warning sign boards of roads is
Answer. -
9) Question.
The number of vehicles moving in a specified direction on a roadway that pass a given point during specified unit of time, is called
Answer. -
10) Question.
The total value of extra widening required at a horizontal curve on a two lane hill road of radius 42 m for a design speed of 50 kmph and for vehicles with wheel base 6 m, is
Answer. -
11) Question.
The superelevation to be provided in horizontal curves of radius R in hill roads is given by -
Answer. -
12) Question.
Rapid curing cutback bitumen is produced by blending bitumen with -
Answer. -
13) Question.
When two roads with two-lane, two-way traffic, cross at an uncontrolled intersection, the total number of potential major conflict points would be -
Answer. -
14) Question.
Brake is applied on a vehicle which then skids a distance of 16 m before coming to stop. If the developed average coefficient of friction between the tyres and the pavement is 0.4, then the speed of the vehicle before skidding would have been nearly -
Answer. -
15) Question.
The camber for hill roads in case of bituminous surfacing is adopted as -
Answer. -
16) Question.
A hill road is one which passes through a terrain with a cross slope of -
Answer. -
17) Question.
In highway construction on superelevated curves, the rolling shall proceed from -
Answer. -
18) Question.
The most suitable equipment for compacting clayey soils is a -
Answer. -
19) Question.
Most suitable material for highway embankments is -
Answer. -
20) Question.
In the penetration macadam construction, the bitumen is -
Answer.