Concrete Technology Sheet 9
-
1) Question.
The coefficient of shrinkage for high grade concrete for pretensioned work is
Answer. -
2) Question.
Prestress loss due to friction occurs
Answer. -
3) Question.
Which of the following losses of prestress occur only in pretensioning and not in post-tensioning
Answer. -
4) Question.
Most common method of prestressing used for factory production is
Answer. -
5) Question.
Normally prestressing wires are arranged in the
Answer. -
6) Question.
The purpose of reinforcement in prestressed concrete is
Answer. -
7) Question.
The creep strains are
Answer. -
8) Question.
For bars in tension, a standard hook has an anchorage value equivalent to a straight length of
Answer. -
9) Question.
The development length of bars of diameter ¢ , as per IS: 456-1978 is given by
Answer. -
10) Question.
According to the IS: 456-1978, the maximum strain in concrete at the outermost compression fibre in the limit state design of flexural member is
Answer. -
11) Question.
The bulk density of aggregates depends upon its -
Answer. -
12) Question.
The most useless aggregate is, whose surface texture is -
Answer. -
13) Question.
The construction joints are generally provided in concrete -
Answer. -
14) Question.
The construction joints in cement concrete -
Answer. -
15) Question.
In concrete walls, construction joints should be provided at the -
Answer. -
16) Question.
Vertical sides of columns may be stripped after -
Answer. -
17) Question.
Under normal circumstances, the beam soffits may be removed after -
Answer. -
18) Question.
Proper curing of cement concrete, is good for its -
Answer. -
19) Question.
After the curing of 28 days, the concrete gains strength upto -
Answer. -
20) Question.
The object of curing is to -
Answer.